April 10, 2008 ---Manager’s Report

For your consideration:

 

Water & Sewer   --- Issues & Updates

  1. Water & Sewer Distribution Upgrade Plan

 

Sewer:

 

First In-Town sewer project is complete.

 

Pre - construction conference was held with Boring Contractors, Inc, Abingdon , Virginia on April 2, 2008 . Boring has been issued a Notice To Proceed effective May 1, 2008 . Contract has a completion time of 315 days.

 

Water:       

Chilhowie Street – Line 400: As of  March 6, 2008 :                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                              110’ of 6” water line, 36’of 6” ductile iron, 70’of  Ύ” service line, 1 meter box, and 1 fire hydrant have been installed. 37 tons of gravel has been used. 4 meters have been hooked up. March 4th and 5th rain kept us from working on the project, but we did haul gravel for the project. On March 7th t he construction crew was pulled from Chilhowie St. to Old Stage Rd. VDOT is going to pave Old Stage Rd, so they were moved to complete the project before it was paved.

 

Old Stage Road – Line 1100:  As of March 7, 2008 thru March 27, 2008 :

2160’ of 6” water line, 231’ of 6” ductile iron,129’of Ύ” service line, 10’ of 4” water line, 5’ of 1” water line, 1 fire hydrant, 11 meter boxes,  4 – 6” gate valves, and 1 – 4” gate valve have been installed. 580 tons of gravel has been used. We will be continuing work on Old Stage Rd. until it is complete and will then move back to Chilhowie Street .

 

  1. Leak Detection & Repairs

Leaks being detected and repaired as needed. Ultrasound flow meter has been purchased to help resolve low accountability problems on West End . Investigation and repairs being completed in Tiny Town Trailer Park on leaks, inadequate size lines, and replacement of lines.

 

 

c.   Purchase two (2) pick-ups from state contract to replace four (4) Public Works vehicle requiring repairs.

 

Personnel   ---Issues & Updates

No actionable items.

 

Finance   ---Issues & Updates

No actionable items.

 

Building & Grounds   --- Issues & Updates

 

a.  Chilhowie Walking Trail

 

Lane Engineering has received the “50% plans” back from VDOT with comments. “90% plans” will be resubmitted by April 18, 2008 .

The anticipated schedule is as follows:

 

Advertisement Construction

          Receive Bids                                        June 15, 2008

          Request  to Award sent to VDOT           June 20, 2008

          Receive Approval VDOT to Award                   July 20, 2008

          Agreement with Contractor                             August 7, 2008      

Preconstruction Conference                   August 7, 2008

          Start Construction                                August 9, 2008

          Complete construction                          December 15, 2008

NOTE: This schedule is dependent on timely responses from VDOT.

 

b.  H.L Bonham Center

 

No actionable items.

  1. Old High School

No actionable items.

  1. Little League Field

No actionable items.

 

 

  1. Loman's Store

 

Smyth County Building Inspector has required a structural analysis prior to issuing a building permit for removing part of the walls. Lane architect has reviewed structure on 4/8/08 and will be issuing report to submit to Building Inspector.

 

Recreation, Arts & Tourism   ---Issues & Updates

No actionable items.

 

Sanitation, Streets, Lights, & Technology

No actionable items.

 

Old High School    -- Issues & Update

          Jim Bonham to give update at Council

 

Fire/EMS & Police   --- Issues & Updates

No actionable items.

 

Miscellaneous   ---Issues & Updates